Clause Centre

The Clause That Turned the Subcontractor into the Payer - How a bespoke JCT amendment transformed a valuation dispute into a jurisdictional knockout

13 September 2026
Clause Text
The Clause That Turned the Subcontractor into the Payer
 
Clause 4.7A.2 (Schedule of Amendments) 
“If in the case of any interim payment a balance is due to the Contractor, it shall be shown as such in the Contractor's Payment Notice under clause 4.7.2. If the Sub-Contractor intends to pay less than the amount so shown, he shall not later than 7 days before the final date for payment give the Contractor notice of that intention, stating the sum, if any, that he considers due to the Contractor at the date he gives notice and the basis on which that sum has been calculated. If the Sub-Contractor gives such notice, the sum to be paid on or before the final date for payment shall not be less than the amount stated as due in the Sub-Contractor's notice. Failing payment of any amount properly due to the Contractor by the final date for payment, interest shall be payable by the Sub-Contractor on that amount at the rate specified in clause 4.7.7.”
Why is this clause problematic?

At first sight, clause 4.7A.2 appears to be a straightforward accounting mechanism. It allows an interim valuation to produce a balance in favour of the contractor and requires the subcontractor to serve a notice if it wishes to pay less.

The difficulty lies in what happens if that mechanism interacts successfully with the Housing Grants, Construction and Regeneration Act 1996.

Once the clause expressly contemplated:

"a balance due to the Contractor"

during an interim payment cycle, it became possible to argue that the usual payment roles had been reversed. In relation to that particular payment, the contractor became the payee and the subcontractor became the payer.

That argument set off a chain reaction.

The contractor contended that:

  1. its Payment Notice became a notice under section 110A(3) of the Construction Act;
  2. the amount stated became a statutory "notified sum" under section 111;
  3. clause 4.7A.2 provided the equivalent of a pay less notice mechanism;
  4. the subcontractor failed to serve such a notice;
  5. an immediate statutory payment obligation therefore arose.

Once that position was reached, the contractor argued that the authorities in Grove, Davenport, Bexheat, Lidl and VMA applied.

The consequence was dramatic.

The dispute ceased to be a valuation dispute and became a jurisdiction dispute.

What were the cost consequences?

The subcontractor commenced an adjudication seeking decisions concerning measured works, ground conditions, culvert works, dayworks, contra charges, retention and loss and expense.

The contractor argued that these were not standalone claims. They were all matters that could previously have been raised through the payment machinery created by clause 4.7A.2.

If the contractor was correct, the adjudication was in substance a true value adjudication.

The problem for the subcontractor was that under the authorities following Grove, a party cannot normally commence a true value adjudication whilst an existing notified sum remains unpaid.

The issue therefore became:

Did clause 4.7A.2 create a statutory notified sum which had to be paid before the adjudication could be started?

That was the question which dominated the adjudication.

The parties devoted extensive submissions to:

  • whether the contractor could be the payee;
  • whether the subcontractor could be the payer;
  • whether the payment notice satisfied section 110A;
  • whether the amount stated became a notified sum;
  • whether clause 4.7A.2 operated as a pay less notice mechanism;
  • whether an immediate payment obligation arose.

The adjudicator ultimately concluded that the contractor's argument was correct.

In particular, he concluded that:

  • the amendment expressly allowed an interim balance to be due to the contractor;
  • the contractor could therefore be the payee for that payment;
  • the payment notice was capable of operating as a section 110A(3) notice;
  • the amount stated became the notified sum;
  • clause 4.7A.2 operated as the contractual pay less mechanism;
  • the subcontractor had not served a compliant notice;
  • an immediate payment obligation arose;
  • that payment obligation remained unsatisfied when the adjudication began.

Having reached those conclusions, the adjudicator further found that the adjudication was, in substance, a true value adjudication that sought to revisit matters that could already have been addressed through the contractual payment machinery.

Applying Grove, Davenport, Bexheat and Lidl, he therefore concluded that he lacked jurisdiction to continue.

The result was unusual.

The adjudicator never determined the valuation dispute.

He never decided the claim.

Instead, the payment clause operated as a gateway issue. Once the clause was found capable of creating an unpaid notified sum, the adjudication was effectively stopped before the substantive dispute could be heard.  The Subcontractor had to pay the adjudicator's fees to the point of resignation.

In short:

The clause converted what the parties thought was a valuation adjudication into a payment-jurisdiction adjudication. Once the payment argument succeeded, the valuation dispute could not even be reached.

This clause exposed a party to procedural risk.

Its significance was not that it changed the valuation.

Its significance was that it potentially changed who was the payer, who was the payee, whether a notified sum existed, whether payment had to be made immediately, and ultimately whether an adjudicator had jurisdiction to hear the dispute at all.

That is why a relatively short amendment resulted in the adjudicator resigning without deciding the merits of the case.

Amendment to Standard Form
Associated Clauses

1. Clause 4.6.1 - Due Date Mechanism

Clause 4.6.1 established when interim payments became due:

"the monthly due dates for interim payments shall in each case be the date 14 days after the relevant Interim Valuation Date..."

This clause fixed the payment cycle and therefore determined:

  • the due date;
  • the timing of any Payment Notice under clause 4.7.2;
  • the final date for payment under clause 4.7.1.

Without clause 4.6.1 there would have been no framework within which clause 4.7A.2 could operate.

2. Clause 4.7.1 - Final Date for Payment

Clause 4.7A.2 required any pay less notice from the subcontractor to be given:

"not later than 7 days before the final date for payment"

Accordingly, clause 4.7.1 was critical because it determined the final date against which the clause 4.7A.2 timetable was measured.

The contractor's argument depended on demonstrating that:

  • a notified sum existed;
  • no compliant clause 4.7A.2 notice had been served;
  • the final date for payment had expired.

Only then could an alleged immediate payment obligation arise.

3. Clause 4.7.2 - Payment Notice

This was arguably the most important clause associated with clause 4.7A.2.

It required the Contractor to issue a Payment Notice:

"specify the sum that he considers to be or have been due at the due date and the basis on which that sum has been calculated."

The adjudicator concluded that because clause 4.7A.2 expressly required any balance due to the Contractor to be shown in the clause 4.7.2 Payment Notice, the two clauses had to be read together.

The contractor's entire jurisdiction argument depended upon treating:

  • clause 4.7.2 as the notice mechanism; and
  • clause 4.7A.2 as the corresponding pay less mechanism.

If that analysis failed, the notified sum argument collapsed.

4. Clause 4.7A.2 - The Critical Amendment

This was the clause at the centre of the dispute.

The crucial features were:

  • recognition that an interim valuation could produce a balance due to the contractor;
  • an obligation on the subcontractor to serve notice if it intended to pay less;
  • an obligation to state the amount considered due;
  • a contractual interest provision if the balance remained unpaid.

These provisions effectively mirrored a conventional payment notice/pay less notice structure, but with the payment direction reversed.

5. Clause 4.7.7 - Interest

Clause 4.7A.2 expressly incorporated clause 4.7.7 by providing that:

"interest shall be payable by the Sub-Contractor"

if payment was not made.

This reinforced the proposition that the amendment was intended to create a genuine payment obligation, not merely a valuation exercise.

The contractor relied on this wording as further evidence that the parties intended interim balances payable by the subcontractor to be recoverable as debts.

6. Contractual Priority Clause

Perhaps the most overlooked associated provision was the hierarchy clause within the Schedule of Amendments.

The adjudicator relied on the fact that the bespoke amendments were expressed to prevail over inconsistent standard form provisions.

This was important because the subcontractor argued that elsewhere in the standard JCT subcontract the payment provisions contemplate payments flowing only to the subcontractor.

The adjudicator rejected that argument because:

  • clause 4.7A.2 expressly addressed interim balances due to the contractor; and
  • the amended provisions took precedence over inconsistent standard form wording.

Without the hierarchy provision, there may have been an argument that clause 4.7A.2 conflicted with the remainder of the payment regime.

ClauseWatch Insight

The real lesson is that the problematic clause was not clause 4.7A.2 alone.

The jurisdiction argument only worked because clause 4.7A.2 interacted with:

  1. Clause 4.6.1 (establishing the due date);
  2. Clause 4.7.1 (establishing the final date for payment);
  3. Clause 4.7.2 (establishing the contractor's payment notice);
  4. Clause 4.7.7 (interest on unpaid sums); and
  5. the contractual hierarchy provisions (giving priority to the amendment).

Taken together, those provisions arguably created a complete statutory payment regime in which:

  • the contractor became the payee;
  • the subcontractor became the payer;
  • a notified sum arose;
  • a pay less mechanism existed; and
  • an immediate payment obligation was capable of arising.

That integrated payment regime is what ultimately led the adjudicator to conclude that the subcontractor had commenced a true value adjudication before satisfying an existing payment obligation, resulting in the adjudicator upholding the jurisdiction challenge and resigning.

Relevant Case Reference

The authorities fall into three categories:

1. The "Pay Now, Argue Later" Authorities

These establish the principle that an unpaid notified sum must generally be paid before a true value adjudication can be pursued.

S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448

Principle

The Court of Appeal held that the payer must first comply with its immediate payment obligation arising from a valid payment notice regime before commencing a true value adjudication.

Why it mattered here

The contractors's entire jurisdiction challenge was built upon the proposition that clause 4.7A.2 created a notified sum of £153,310.74. If so, the subcontractor had to pay first and argue later.

ClauseWatch takeaway

The genesis of the "pay now, argue later, value later" principle.


M Davenport Builders Ltd v Greer [2019] EWHC 318 (TCC)

Principle

Payment of the notified sum is a precondition to commencing a subsequent true value adjudication.

Why it mattered here

The adjudicator concluded that the alleged payment obligation remained unsatisfied when the adjudication was commenced.

This was the authority most directly supporting the proposition that the adjudication was premature.

ClauseWatch takeaway

Failure to pay can prevent the true value adjudication from getting off the ground.


Bexheat Ltd v Essex Services Group Ltd [2022] EWHC 936 (TCC)

Principle

Reaffirmed Grove and Davenport.

The right to commence a true value adjudication is subordinate to the immediate payment obligation.

Why it mattered here

The contractor relied upon Bexheat to support the proposition that compliance with the payment obligation was not optional or merely procedural.

ClauseWatch takeaway

The true value right is subjugated to the payment obligation.

2. The Scope of the Restriction

Lidl Great Britain Ltd v Closed Circuit Cooling Ltd t/a 3CL [2023] EWHC 3051 (TCC)

In many ways this was the most important authority.

Principle

The Court held that the inquiry is one of substance rather than form.

The Court asked:

Could the matters now being pursued have been raised through the notice/payment machinery applicable to the earlier payment cycle?

If yes, Grove may apply.

If no, Grove may not apply.

Why it mattered here

The subcontractor argued that its referral was made up of multiple claims including Variations, contra-charges and loss and expense.

The contractor argued that all of those matters had already arisen and could have been raised during the relevant payment cycle.

The adjudicator accepted that argument.

The Lidl analysis therefore became critical.

Without Lidl, the subcontractor would have had a stronger argument that this was simply a different dispute.

ClauseWatch takeaway

It is the substance of the dispute, not the label attached to it, that matters.

3. The Recent Confirmation

VMA Services Ltd v Project One London Ltd [2025] EWHC 1815 (TCC)

Principle

Reaffirmed the Grove line of authority.

Importantly, the immediate payment obligation exists regardless of whether the receiving party has first obtained an adjudicator's decision enforcing payment.

Why it mattered here

The subcontractor's position effectively required the contractor first to obtain enforcement of the alleged debt.

The contractor argued that no such step was necessary.

The adjudicator accepted that the payment obligation could arise before any separate adjudication to recover the money.

ClauseWatch takeaway

A notified sum does not cease to be immediately payable merely because nobody has yet sued for it.

4. The Hidden Authority

Jawaby Property Investment Ltd v The Interiors Group Ltd [2016] EWHC 557 (TCC)

This was relied upon by the subcontractor.

Principle

The statutory payment regime requires payment of the notified sum.

However, the case involved the conventional payment structure where money was flowing to the contractor.

Why it mattered here

The subcontractor used Jawaby to argue:

A notified sum is something payable by a payer to a payee. It is not intended to create an interim payment obligation running in reverse from subcontractor to contractor.

This was one of the central legal objections to the contractor's analysis.

The adjudicator ultimately rejected that submission because of the bespoke drafting of clause 4.7A.2.

ClauseWatch takeaway

The case highlights why the amendment was so unusual: it attempted to use statutory payment machinery in a manner not normally encountered in interim payment cycles.

Contract Type
Subcontract
Jurisdiction / Region
Clause Function Category
Payment
Variations
Liquidated Damages
Others
Risk Type
Non-Payment / Late Payment
Interpretation / Legal Classification Dispute
Known outcomes?
Led to dispute
Adjudicated
Clause BEE Score
Bias 2
Exposure 5
Enforceability 4

Community Contributions

Comments are subject to our site participation guidelines and moderation policy, which can be viewed here. By joining the conversation, you are accepting our site rules and terms. Please note our policy is for readers to use their real names when commenting.

Contribute

Reminder - The Three Dimensions

1. Bias (B-Score)

How is risk structurally allocated?

  1. Extreme Imbalance
  2. Significantly Unfair
  3. Moderately One-Sided
  4. Slightly Skewed
  5. Balanced

Higher numbers indicate increasing allocation of risk to one party.

2. Exposure (E-Score)

What happens if the clause operates?

  1. Severe / Litigation Likely
  2. High-Risk Outcome
  3. Material Exposure
  4. Manageable Impact
  5. Low Consequence

Higher numbers indicate greater real-world cost, delay, or dispute risk.

3. Enforceability (Enf.)

Is the clause likely to be upheld and applied as written?

  1. Highly likely to be enforced
  2. Generally enforceable
  3. Contestable / uncertain
  4. Legally vulnerable
  5. Unlikely to be enforced

Higher numbers indicate greater likelihood of legal effect.