2.14A Insert new clause 2.14A to JCT DBSub/C 2016 as follows: “2.14A - Errors and omissions in Employer's Requirements and Contractor's Proposals
Under standard JCT principles, a contractor would usually expect relief where there are defects or inconsistencies in information supplied from above. This clause transfers responsibility for errors, omissions and inconsistencies in the Employer's Requirements and Contractor's Proposals to the Sub-Contractor.
The Sub-Contractor loses entitlement to additional payment, extensions of time and other relief arising from design defects or coordination errors that originated in documents prepared by others. The clause frequently becomes contentious where the true scope of work proves materially greater than indicated during tendering.
The clause can have severe financial consequences. Costs arising from design errors, omissions or inconsistencies in documents supplied by the contractor may become irrecoverable. On a Sub-Contract valued at £200,000, even a modest 10% increase in the work arising from a document error could leave the Sub-Contractor carrying over £20,000 of unrecoverable cost, together with any associated delay and disruption expenses.
Where completion is delayed, the Sub-Contractor may also become exposed to liquidated damages and additional preliminaries costs. The real ClauseWatch lesson is not simply that the clause is onerous but that it creates "blind risk assumption": the Sub-Contractor is asked to accept liability for defects in information it neither created nor controlled.
The amendment transfers the risk of design errors and inconsistencies in upstream contract documents from the Contractor to the Sub-Contractor, removing the Sub-Contractor's normal entitlement to claim additional time or money arising from those issues.
The clause does not operate in isolation. It forms part of a wider package of amendments that collectively seeks to transfer design risk to the Sub-Contractor. Most relevant associated clauses:
Clause 2.13.1 The Sub-Contractor is made fully responsible for the design of the SCD Works, including design contained within the Contractor's Requirements and must verify, correct and complete that design.
Clause 2.13.2 The Sub-Contractor must ensure the design contains no inadequacies or errors and complies with all contractual and statutory requirements. Contractor review or approval provides no relief from that responsibility.
Clause 2.13.4 Where an inadequacy or error is found within the Contractor's Requirements, the Sub-Contractor must correct it at its own cost and without entitlement to a variation or extension of time.
Clause 2.14.1 Expands the concept of design discrepancies to include errors, inadequacies and divergences within or between the SCD Documents.
Numbered Document provision Clause 2.2 The Sub-Contractor is deemed satisfied as to the feasibility of the Employer's Requirements and accepts full responsibility for design contained within them.
Numbered Document provision Clause 2.3 The Sub-Contractor agrees to undertake the verification, development and completion of the design.
Together, these provisions seek to create a comprehensive risk-transfer regime under which the Sub-Contractor assumes responsibility for identifying and absorbing the consequences of design deficiencies originating elsewhere.
The courts may enforce clear contractual wording transferring responsibility for design adequacy to the contractor or subcontractor, even where the relevant design information originated elsewhere. See MT Højgaard A/S v E.ON Climate & Renewables UK Robin Rigg East Ltd [2017] UKSC 59.
Comments are subject to our site participation guidelines and moderation policy, which can be viewed here. By joining the conversation, you are accepting our site rules and terms. Please note our policy is for readers to use their real names when commenting.
1. Bias (B-Score)
How is risk structurally allocated?
Higher numbers indicate increasing allocation of risk to one party.
2. Exposure (E-Score)
What happens if the clause operates?
Higher numbers indicate greater real-world cost, delay, or dispute risk.
3. Enforceability (Enf.)
Is the clause likely to be upheld and applied as written?
Higher numbers indicate greater likelihood of legal effect.