The clause contains two distinct elements:
A court or adjudicator may uphold the first element as an agreed contractual mechanism, particularly where the Main Contractor is selecting between two genuinely plausible interpretations. The second element is more vulnerable, especially where the Main Contractor's decision effectively changes the scope, imposes additional work, or overrides an express valuation or variation provision.
Assuming England and Wales law, the clause is intended to transfer most of the financial risk of inconsistencies and ambiguities to the Sub-Contractor.
Its practical cost consequences are likely to be:
However, the clause should not automatically deprive the Sub-Contractor of payment where the Main Contractor's decision:
The key financial distinction is therefore:
If the Main Contractor is merely choosing between two genuine interpretations of the original scope, the Sub-Contractor may bear the additional cost. If the Main Contractor is changing or enlarging the scope, the work may remain separately payable despite the clause.
The clause may also affect recovery of adjudication or litigation costs only indirectly. In statutory adjudication, each party normally bears its own legal costs unless the parties validly agree otherwise after the dispute has arisen. The clause itself does not appear to be an express costs-shifting provision.
For tendering purposes, the safest approach is to identify every known ambiguity expressly, state the pricing assumption adopted, and provide that any departure from that assumption is a variation.
Not applicable.
Note applicable.
None come immediately to mind but since the clause appears in the Main Contractor’s written standard terms, the Unfair Contract Terms Act 1977 may be relevant. In particular, section 3 can subject a term to the statutory reasonableness test where one party deals on the other’s written standard terms and the term permits that party to:
A clause excluding or restricting liability for breach may also require scrutiny under UCTA. Relevant considerations include bargaining strength, negotiation, insurance, awareness of the term, and whether the risk could realistically have been priced.
UCTA is less likely to intervene where the clause was individually negotiated between commercially sophisticated parties, although the question remains fact-sensitive.
Comments are subject to our site participation guidelines and moderation policy, which can be viewed here. By joining the conversation, you are accepting our site rules and terms. Please note our policy is for readers to use their real names when commenting.
1. Bias (B-Score)
How is risk structurally allocated?
Higher numbers indicate increasing allocation of risk to one party.
2. Exposure (E-Score)
What happens if the clause operates?
Higher numbers indicate greater real-world cost, delay, or dispute risk.
3. Enforceability (Enf.)
Is the clause likely to be upheld and applied as written?
Higher numbers indicate greater likelihood of legal effect.